The Municipality of Concordia, through the Secretariat of Urban Development, continues this Wednesday, June 18, with the program for the repair of unpaved streets as well as pothole patching in different sectors and neighborhoods of the city.
The sectors where work will be carried out during the day are as follows:
Benito Legerén: Profiling and repair of Avenida de Los Trabajadores, between Parque Industrial and San Cayetano.
Bus Lines: Grading of La Pampa and Gualeguay streets between 11 de Noviembre and Presidente Illia; Sauré between Diamante and 2 de Abril
Grading of Paula Albarracín streets between España and Sara Neira; Odiard, De Los Viñedo; Laprida between Italia and Sara Neira; Mario Gatto.
Grading of Odiard streets between Moulins and Presidente Illia; Gregoria Pérez from Boulevard Ayuí to Antonio Báez and Ramón Arias to Moulins. Then along Moulins to Vera Peñaloza between Presidente Illia and Ricardo Rojas and Ricardo Rojas, between Paula Albarracín and Vera Peñaloza.
Grading of Pampa Soler streets between Boulevard Ayuí to Segundo Sombra and Eva Perón, between Segundo Sombra and Sargento Cabrera, Jujuy and Hipólito Yrigoyen.
Calle Misiones and the area: Grading between San Lorenzo and Salto Uruguayo; Rocamora, Victorino Simón from Salto Uruguayo to San Lorenzo; Echague between Maipú and the river.
Cleaning of micro-landfills on Córdoba and Villaguay streets
Opening and compaction of potholes on Boulevard Yuquerí streets, between Ricardo Rojas and Gregoria Pérez; La Pampa between República del Paraguay and San Lorenzo.
Concrete pouring on Eva Perón street between Antártida Argentina and Boulevard Ayuí.
The sectors where work will be carried out during the day are as follows:
Benito Legerén: Profiling and repair of Avenida de Los Trabajadores, between Parque Industrial and San Cayetano.
Bus Lines: Grading of La Pampa and Gualeguay streets between 11 de Noviembre and Presidente Illia; Sauré between Diamante and 2 de Abril
Grading of Paula Albarracín streets between España and Sara Neira; Odiard, De Los Viñedo; Laprida between Italia and Sara Neira; Mario Gatto.
Grading of Odiard streets between Moulins and Presidente Illia; Gregoria Pérez from Boulevard Ayuí to Antonio Báez and Ramón Arias to Moulins. Then along Moulins to Vera Peñaloza between Presidente Illia and Ricardo Rojas and Ricardo Rojas, between Paula Albarracín and Vera Peñaloza.
Grading of Pampa Soler streets between Boulevard Ayuí to Segundo Sombra and Eva Perón, between Segundo Sombra and Sargento Cabrera, Jujuy and Hipólito Yrigoyen.
Calle Misiones and the area: Grading between San Lorenzo and Salto Uruguayo; Rocamora, Victorino Simón from Salto Uruguayo to San Lorenzo; Echague between Maipú and the river.
Cleaning of micro-landfills on Córdoba and Villaguay streets
Opening and compaction of potholes on Boulevard Yuquerí streets, between Ricardo Rojas and Gregoria Pérez; La Pampa between República del Paraguay and San Lorenzo.
Concrete pouring on Eva Perón street between Antártida Argentina and Boulevard Ayuí.